TITLE : Progress Report

 

 

 

 

 

WRITTEN BY : M.Borghi

 

 

 

SUMMARY : MOSAIC activities (May/June/July months)

 

No part of this document can be reproduced, in any form, or by any means, prior to written authorization of the

MOSAIC Consortium

 

 

Table of Contents

 

1. SUMMARY 3

2. MANAGEMENT 3

3. TECHNICAL 7

4. PO PROGRESS 14

5. ANNEX A : MOSAIC ACTION ITEMS LIST 15

6. ANNEX B : CONFIGURATION STATUS ACCOUNTING LIST 16

7. ANNEX C : PLANNING 16

 

 

Summary

The document describes the main activities in MOSAIC done by Contractors and Participating Organisation during the initial quarter May/June/July.

Management

The main management activities performed have been:

contractual issues clarification (Kick-off meeting) and P.O. subcontract preparation and signature

web site organization, definition and activation

project standard and tools definition

MOSAIC Flyer design

Report format design

meeting organization :

May 29th 1997 MOSAIC kick-off - Brussels

June 2nd 1997 MOSAIC internal kick-off - Rome

June 5th 1997 MOSAIC presentation MOU event - Brussels

June 27th 1997 MOSAIC presentation day - Rome

July 28th 1997 "Entretiens de Paris sur le devenir de l'action culturelle - europeenne" - Paris

July 29th 1997 Coordination Meeting - Paris

secretary-project organisation and start-up

During the Paris meeting the following agenda has been proposed :

13th September - Working meeting in Milan (organised by Politecnico di Milano)

Third week of October - Working meeting in Paris (organized by Arenothec)

Third week of November - Mid term review with demonstration session (to be organized in accordance with suggestions of Eu Commission)

Third week of December - Working meeting at Darmstadt or at Graz

Each meeting will be organised on two days:

first day for the working in progress analysis and the review or discussion of the WP documents

second day for the presentation of the project to the potential partners looking for new sponsors

The MOSAIC web has been created in order to manage the project and disseminate information to all the partners and contractors (http ://mosaic.bancaroma.it ). The first network of MOSAIC, has been activated in following cities: Bologna, Darmstadt, Graz, Milano. The MoU web hosting and related forum has present in MOSAIC server. The main links are : (1) Partners, (2) Project, (3) Other Projects, (4) Info, (5) Form, (6) Demos, (7) News, (8) Intranet Web Tools.

"Partners" - information about : (1) MOSAIC Consortium ("the Coordinator" and "the Contractors"), (2) Additional Partners (other Cultural Operators) (3) How to join (how to obtain more info, to receive an account for MOSAIC, to support MOSAIC, to send remarks/suggestions)

"Project" - information about : (1) Contractual Documentation (Contract, Planning, Deliverables List, Work Packages), (2) Technical Documentation, (3) Events (MOASIC events), (4) Dead line check and control(MOSAIC deliverables), (4) Report

"Other Project"- web links of MOSAIC related projects. Actually new links have been added to the following EU projects : AQUARELLE, CHIO, IMPRIMATUR, MOU

"Info" - abstract of MOSAIC project

"Forum" to have a cyber-net debate about MOSAIC and spread the cultural heritage dissemination.

"Demos" presentation of tools, services and applications related to the MOSAIC project.

"News" contains a list of MOSAIC related events and a "Press" area

"Intranet" contains useful documents for entities involved in MOSAIC project. At moment is present: Documentation (Digital library, Related non-EU projects, MOSAIC logo forum), Download Area  (standard document, report layout, compression tools, telecommunication tools, Site download)

"Web Tools" contains tools for MOSAIC web users. A demo for flashpix and WRML has activated

Access to "Project" and to "Intranet" is allowed through the usage of a password. Access to the "Press" (in Info) also requires a password.

The MOSAIC logo has been produced. It is the outcome of the various stages experienced by the graphic alphabet, it is a fundamental mean for communication and culture. It is the synthesis of the graphic excursus, which goes from the Roman inscriptions, through Charlemagne, with the Caroline writing, who was the promoter of the unity of the western graphics, to the Renaissance harmonization and the XIX century ornate style. The colours of the logo come out from an artistic elaboration of a detail of the EU flag, as an interpretation of the contents of the project MOSAIC.

An open e-mail has been activated on the web. It is mosaic@bancaroma.it.

The four registration forms for "Potential Partners", "Information Request", "User Registration", "Remarks" have been activated.

July 1st  the output of workpackage 1100 (Survey on the state of the Art) has been inserted on the MOSAIC web both in HTML and .doc format

July 7th  a new MOSAIC web zipped version is downloadable

The MOSAIC communication and presentation tape is in progress.

The divulgation meeting abstracts have been translated and they will be available on the web in September.

 

 

Technical

The following table illustrates a synthesis of the work in progress.

WP number

description

status

WP 1100 Survey of the "state of the art"

in progress

WP 1200 Market plan

starting

WP 1300 Partner search and economical agreement definition

20%

WP 1400 Target User profile definition

75%

WP 1500 Requirements definition, tools, service centers, application

starting

WP 1600 Study for the reuse of existing applications into the defined architecture  
WP 1700 Architecture definition and tools definition  
WP 1800 Dissemination of results  
WP 1900 Management

25%

WP 2000 CSC model demonstrator

10%

 

Planning modification has been introduced to improve the feasibility study.

Due to the presence of important events in August (Siggraph 97 - Los Angeles) and in September (ICHIM 97 - Paris), we decided to update our acknowledge with the outputs of these conferences and update the WP 1100 (survey on the state of the art). Similar considerations have been done for the WP 1400. In fact in both manifestations interviews were scheduled to obtain info to refine the WP 1400 document. WP 1500 is scheduled on time because it will start anyway on the base of the existing draft.

The WP 2000, has been activated in order to obtain some tools and services on line. The main elements will be presented in the demo area of the mosaic web.

The main technological goals of the next events, are :

August 1st – 10th: ACM Siggraph 97 in Los Angeles – annual international conference and exhibition devoted to computer graphics and multimedia. Is still one of the easier world-wide occasion to meet in one site and in a few days only experts, researchers and top line companies (please refer to Siggraph 97 web-www.siggraph.org/s97/).

TEN telecom programme is a market oriented framework, the main issue of TEN projects is to create and deliver trough the network new ‘smart’ services mainly using or re-using existing technologies (this is not a research framework). MOSAIC is consequently based on networks, VR and hypermedia applications selected from the full range of existing and quickly evolving technologies. The WPK 1100 outlined some of such technologies like "flashpix" hi-res imaging system (Kodak, MS, HP ..), SUMS programme universal media searching system, HTML 3.2 active pages, VRML, infinity resolution IVR and so on. People and companies working on such technologies will be at Siggraph and on such occasion will probably outline the future developments of their studies. This will be useful to consolidate the development of MOSAIC and create joint projects. MOSAIC will probably take advantage of using "Lightscape" capability to navigate in real time VR fine digital reconstruction of architectural artworks. Hi performance, low price head mounted display will be probably used in MOSAIC Cultural Service Centers or home based applications and the same may apply to 3D navigation devices. Canadian indexing systems are surely world-wide very well known. Attending Siggraph we will meet and enforce even existing relationships with such companies. Some meetings with experts and companies are already scheduled. Due to the even increasing market and high speed of development in IT we plan to update and tune our survey on the state of art and consequently MOSAIC standards (WP 1400 and WP 1500) before the completion of the first year, this thanks to a continuous tracking on emerging technologies and new markets.

On this occasion we will propose a presentation of MOSAIC project first year results as contribution to Siggraph 98 (Orlando FL). We think that MOSAIC will guarantee a multimedia access to Europe’s cultural heritage but as preliminary studies carried out on the possible markets have outlined that USA, CANADA and Japan will probably be the major markets for "Europe’s Cultural Services" and in this perspective disseminating results and techniques at Siggraph "stage" is surely a good start. To reach this goal we have to work very hard with the ACM technical committee.

August 11th – 13th: meetings in San Francisco with SGI, Xerox and other companies for preliminary discussion of technical and economical agreement linked to WPK 1300, 1400, 1600 and 1700

August 14th – 16th: meeting in Redmond (Seattle) Microsoft headquarters for preliminary discussion of technical and economical agreement linked to WPK 1300, 1400, 1500 and 2000

Both the meeting in San Francisco and Seattle are mainly devoted to keep in touch with research centres and technology providers like Xerox PARC leader in human/machine interfaces and network technology or Microsoft laboratories market leader also for home market. And particularly speaking about the role of Microsoft they are actually a reference point for high volume market (the main market to fund cultural heritage services – a big amount of small fees). Another reason to meet people from SGI, Netscape, Apple and Microsoft is the real possibility to promote MOSAIC solution on the market, at least for the first year of implementation, taking advantage of distribution channels linked to widely diffused operating systems and network browsers. The global potential market offered by the internet forces to solve the market approach globally, one possible scenario for MOSAIC may be a bundled system with the most popular products distributed world-wide instead of a never ending sequence of separate agreement with each institution and country. Try to solve self-funding problem using on line transactions, prepaid services and other possible solution in the first period seems not to be the best solution to create a non-existing market.

August 17th – 20th: meeting in Toronto (Canada) with Prof. Kim Veltman’s equipe devoted to SUMS project application to MOSAIC. SUMS (System for Universal Media Searching) was foreseen as primary "search engine" for MOSAIC internet applications.

 

 

 

 

During this period the activities done are mainly related to the WP 1100, 1300, and 1400.

The WP 1100 document has been delivered, but an upgrading is still in progress as above mentioned.

The WP 1300 is in progress and the relevant part of the contact can be summarised as follows :

Meetings & Presentations

EVA 97 Florence – MOSAIC presentation

May 29th Kick Off

June 2nd General Meeting

June 5th MoU meeting

June 6th Museums Group

June 17th MOSAIC presentation in Paris

June 23th Meeting in Madrid

June 24thmeeting in ABI

June 27th MOSAIC Presentation in Roma

June 28thMOSAIC Presentation in Sophia Antipolis

July 6th/11th IEEE ISIE 97 Conference MOSAIC Presentation

July 26th/29th Mosaic consortium meeting - Paris

Main Actions

MOSAIC Web - management of contact

Contacts - Memorandum of Understanding

Contacts with potential partners like CANON, HP, MICROSOFT, SONY, Silicon Graphics, Barco at international level (Europe or World).

Contacts with telecommunications organisation in the world (Telecom, Bell,.etc.)

Contacts with Institutions (Ministry of Culture and Education in all the partner countries, Museums, Galleries, Ministerio della Cultura de Espana, Curia di Milano, ..)

Contacts with local Italian Institution ( Regione Friuli Venezia Giulia, Emilia Romagna, Lazio, Campania,...)

Contacts with Universities in Europe (University of Warwick, Goteborg University - Institute of Conservation, LUISS, Universities linked to the MOSAIC partners,..)

Contacts with MultiMedia Institutions and Service Providers (CCG Portugal, CapCom)

Contacts with the Foundation Sophia Antipolis

Contacts with UNESCO

Contacts with EVA

Contacts with Getty Museum

Contacts with Deutsche Historische Museum, Berlin

Contacts with Athena association

Contacts with VASARI

Contacts with ABI

Contacts with CHIN

Contacts with Kim Veltman G7 - SUM project

Contacts with G7 Pilot Projects CARDIO representative

The following partners has been involved in the activities and in the meetings of the project:

Cad Center Corporation Japan, Mr. Y. Hamano: this company will work to enlarge the institutional partners, to build the Cultural service center and find economical partners in that area.

MAE: the Italian Ministry of Foreign Affairs follows the project and helps the consortium in the relation with institutions of other countries.

ABI: the Associazione Bancaria Italiana has on study a project to manage all the images of the most important cultural properties of the Italian Banks and to make electronic links. They could agree on linking this activity to Mosaic network.

The Conservation Information System - Goteborg University - Institute of Conservation

Infocity project - TEN TELECOM : A letter of cooperation has been received and actually is under analysis.

 

The WP 1400 due activities are manly :

research of references (Bibliography, Internet Address (E-Mail & URLs), Books, Technical Studies, Sociological Studies, Articles, Technological magazines, ..) in order to better define the quality of the services and to classify the user categories.

interviews with potential users (institutional representatives in each state, museums manager and curator, universities, publisher, ....). The synthesis of this work is in progress and new session of interviews has been planned in Siggraphs (stand Infobyte on which Mosaic will be presented) and ICHIM 97 (stand Arenotech and Infobyte on which MOSAIC will be presented).

Actually the document contains the description of the major categories of target user ( Institutions / Museums, Students, Scholars, Researchers, Professors, Managers (Conservatore), Restorator, Artists, Technicians, Publishers, Tourists, Tourist Operators / Agency, Authors, Advertisement, Sponsors, Libraries, Image Agency, Photographers, Merchandise Producers , Art Broker, Interpol / Carabinieri,... ). The first issue of the document will be delivered after the ICHIM manifestation second week of September.

 

WP’s Responsible Partner of activity and Deliverables
1 - WP1100

Survey on the state of the art

Responsible :

DISET :

T0 -> T0+1

Milestones :

none

DISET

Joanneum Research

Arenotech

 

Deliverables :

State of the art technical notes

Recommendation for the architecture

2 - WP1200

Market Plan

Responsible :

BDR :

T0+3->T0+10

Milestones :

T0+12 Assessment on feasibility study

Banca di Roma

Arenotech

 

Deliverables :

Business Plan Document

 

 

1 - WP1300 

Partner Research and Economical Agreement Definition

Responsible :

DISET

T0->T0+12

Milestones :

T0+12

Assessment on feasibility study

DISET

Arenotech

Banca di Roma

 

Deliverables :

Participation letters list updated

Test mutual agreement contract ready to be used during the deployment

 

 

1 - WP1400 

Target User Profile Definition

Responsible :

ARENOTECH

T0->T0+4 (delay of one month)

Milestones :

none

Arenotech

Infobyte

 

Deliverables :

Target user profile specification

 

 

2 - WP1500

Requirements, Tools, Service Centers, Application

Responsible :

INFOBYTE :

T0+3-> T0+6

Milestones :

T0+6 Requirements review

Joanneum research

Arenotech

DISET

ZGDV

Infobyte

 

Deliverables :

Requirements definition document

3 - WP1600

Study for the Reuse of existing Application into the Defined Architecture

Responsible :

Joanneum

Research :

T0+6->T0+9

Milestones : none

Arenotech

ZGDV

Joanneum Research

Infobyte

 

Deliverables :

Technical note on application reuse

 

 

3 - WP1700

Architecture Definition and tools definition

Responsible :

INFOBYTE

T0+6->T0+9

Milestones :

none

Infobyte

DISET

Joanneum Research

 

Deliverables :

Architectural Document

 

 

4 - WP1800

Dissemination of results

Responsible :

DISET

T0+9->T0+12

Milestones :

T0+12 Assessment on feasibility study

DISET

Arenotech

CINECA

 

Deliverables :

Workshop, electronic debates, feedback collection book

 

 

0 - WP1900

Management of the MOSAIC project for the feasibility study

Responsible :

BDR

T0->T0+12

Milestones :

T0+12 Assessment of feasibility study

Banca di Roma

 

Deliverables :

progress reports

final report

 

4 - WP2000

CSC model demonstrator

Responsible :

CINECA

T0+8->T0+12

Milestones :

T0+12 Assessment on feasibility study

CINECA

Joanneum Research

DISET

Infobyte

 

Deliverables :

CSC model demonstrator running

 

P.O. progress

The contract between Infobyte and Arenotech has been signed in the 2nd June 1997.

July 8th Arenotech has communicated the availability of its web : http://www.cyberspace.com/oniroland/cuv/home/arenotech.html. A new logo has been produced.

The Arenotech production of "Target User profile specification", that is the output of WP1400, is in progress.

The WP 1300 activities are in progress.

ANNEX A : MOSAIC Action Items List

(updated: 31/07/97)

Ref.: Orig.

Date & Ref.:

Action Short Description Responsible Expected date: Status
  Meeting of Paris 28th July 1997 produce internal monthly progress report to be sent at BDR at the end of each month all partner 1st September 1997

open

  WP 1200 planning define the document layout and activate the joint team for the WP 1200 BDR 20th August 1997

open

  WP 1500

planning

define the document layout and activate the joint team for the WP 1500 INFOBYTE 20th August 1997

open

  September 97 meeting define the detailed agenda and organise the technical and dissemination meeting DISET 1st of September 1997

open

  October 97

meeting

define the detailed agenda and organize the technical and dissemination meeting ARENOTECH 1st October 1997

open

  mid term review meeting define with UE commission the expected documents. Decide the meeting site Graz or Darmstadt . BDR 1st October 1997

open

  November meeting define the agenda and organise the technical and dissemination meeting ZGDV or JRC 1st November 1997

open

  December meeting define the agenda and organise the technical and dissemination meeting JRC or ZGDV 1st December 1997

open

  mosaic web translate the document in French language ARENOTECH September 1997

open

  mosaic web translate the document in German and Spanish language ZGDV September 1997

open

  mosaic tape The MOSAIC tape is under preparation by BDR. Contribution are expected in U-MATIC tape. all partner 1st September 1997

open

  mosaic web activate the web in Italian language CINECA September 1997

open

  MOSAIC LOGO prepare the MOSAIC suggested logos and select the final logo from a short list. all partner 27th July 1997

closed

  payment from UE distribute percentage of founding to the partner BDR 27th July 1997

closed

 

 

ANNEX B : CONFIGURATION STATUS ACCOUNTING LIST

None

 

 

 

ANNEX C : PLANNING - (next page)